Project Manager/Estimator moved into Vice President of Operations and a stock holder – 2006 to 2010
My duties for my latest title of Vice President of Operations were as follows:
Provides day-to-day leadership and guidance to the Superintendent, assisting them in planning, implementing and coordinating project work.
Expected Outcomes:
Position responsibilities:
Made recommendations to President on upcoming projects to bid and or pursue as well as analyzed bids to ensure accuracy.
As an Estimator and Project Manager he bid and managed the following projects:
Started as a carpenter then moved to Foreman, Superintendent, Project Engineer, Project Manager/Estimator
Project Manager/Estimator and satellite office Manager
The role that I held for Bouten construction during the last few years was to open a satellite Office from its conception. Created a business plan and developed the business in the Tri- City area.
As an Estimator and Project Manager he bid and/or managed the following projects.
Sacred Heart Children’s Hospital $17.2 M
Kadlec Medical Center North Building $4.5 M
Kadlec North Tower $36.3 M
CBC Health Science building $8.2 M
Columbia Valley Medical $3.1 M
Open Heart Kadlec Medical $1.5 M
MRI Addition at Lourdes Medical $1.0 M
Carpenter
Performed all phases of being a carpenter.
Carpenter
Performed all phases of being a carpenter.